Final two pandemic-delayed BTO projects completed: HDB

Minister for National Development Desmond Lee has recently released the finalization of the final two pandemic-delayed projects from HDB, according to a Jan 20 launch.

Condo homeowners of Punggol Point Cove (Phase 2) have actually been getting the keys to their brand-new residence from November 2024, while key collection for Kempas Residence began in mid-January this year.

The standing ventures had waiting times of as much as 5 years. Generally, over 18,000 flats were carried out in 2024, states HDB.

HDB is expected to alert the remaining flat proprietors of their key collection date shortly, following the finish of the final blocks within both plans this month.

As at Jan 15, 657 households or 59% of 1,109 booked units have gathered their keys.

At present, 110 HDB home projects are under development, up from 95 a year ago due to the increase in BTO supply in recent years. HDB says it is on track to accomplish around 17,000 flats across 27 plans in 2025.

The two Build-to-Order (BTO) jobs, Punggol Point Cove (Phase 2) and Kempas Residences, note the completion of HDB’s pandemic-delayed housing ventures. As a whole, the 92 plans have delivered over 75,800 new apartments to Singaporeans over the last 5 years.

According to HDB, the finalization of Punggol Point Cove (Phase 2) notes the completion of all flats in the Punggol Point District. This includes Punggol Point Cove (Stage 1), Punggol Point Woods and Punggol Point Crown BTO projects, which were finished in 2024.

The 22 home projects featured two Shorter Waiting Time (SWT) projects, that were finished in just a waiting duration of less than three years. The SWT work, Parc Glen at Tengah and Grove Spring at Yishun, consisted of a total amount of 1,995 flats.

Lakegarden Residences condominium

In 2024, HDB finished a total of 22 home projects, 17 of which were put off by the pandemic. With the exemption of one that was postponed as a result of non-pandemic causes, the remaining four home projects were accomplished promptly.

Positioned around Serangoon Roadway, Lavender Road and Boon Kheng Road, Kempas Residences BTO project has 583 units of two-room flexi, three-, four-room apartments across four residential blocks.

The final block, that was delayed by six months from its first PCD, was completed in mid-January.

Positioned throughout New Punggol Roadway, Punggol Point Cove (Stage 2) consists of 1,179 units of two-room flexi, 3-, 4- and five-room flats across 6 household blocks. Following pandemic hold-ups, the work’s last block was finished 12 months from its original Probable Completion Date (PCD) at an earlier time this month.

As at Jan 15, 37 houses or about 7% of 555 lined up units have gathered their keys.